PIT DESIGN
PIT DESIGN
HEIGHT AND WIDTH OF BENCHES IN OPENCAST MINE
1.In Alluvial,
soil, morum, gravel, clay, debris ( soft over burden), the sides shall
be sloped at an angle
Of safety not
exceeding 45 degree from the horizontal or at an angle Regional inspector
permit.
Kept benched at ht. not exceeding 1.5 m and
width shall not be less than ht.
2. In coal sides shall
be sloped at an angle of safet not exceeding 45 degree from the horizontal or the sides
shall be kept benched not exceeding 3 mtr. In ht..
IN MECHANISED MINE
1.A.Ht.of bench
shall not exceed the maximum reach of m/c used for digging, excavation and
removal.
incase of uniformly soft rock the regional
inspector may permit the extension of the ht. up to 3 mt. above
the digging ht. of the m/c.
B. Width of any bench
shall not be less than
§Width of
any m/c plying on the bench plus 2 mtr.
Or
§If the
dumper is plying on the bench 3 times the width of the dumper.
Or
§Twice the plan length of excavators like shovel and
twice the length of body of m/c like dragline
whichever is more.
Provided that where
dragline used the width of any bench
below in coal /overburden at the finishing stage shall not be less than 3 mtrs.
or
§the ht.
of the bench whichever is more.
§Safety
precaution – when persons are employed within 5m of the
working face adequate precaution shall be taken to ensure their safety by
dressing .
HAUL ROADS
Haul
road is life line in the operation of any opencast mine.
Parameters
for good haul road;
vShall
be to provide one way traffic. Where it is not
practical width shall not be
less than 3 times the width of any m/c plying on the road.
vCorners and bends shall be such that it shall provide
clear view for a
distance of not less than 30mtr. along
the road.
vwhere it is not practicable there
should be separate
two roads for up and down
traffic.
vAt curves super elevation shall
be provided according to speed of the vehicle.
vNo
road shall have gradient less than 1 in 16 at any place.
vRamp over small stretches shall have gradient
up to 1 in 10.
vWhere
any road exist above the level surrounding area , it
shall have
a strong parapet walls or embankments not less than 1 mtr
ht.
v Road
signs shall be provided at every turning points for the guidance of the drivers.
vAt
every curve , parapet walls or vertical posts Zebra lines shall be provided
vThe
portion of surface haul road in mine premises where there is heavy
traffic of men and machines should have separate
lane properly fenced off from the haul road for pedestrians and two
wheelers.
vStandard
traffic signs shall be displayed at conspicuous places alog
the haul road.
v road
surfaces shall be maintened smooth and of sufficient strength.
vLoaded
trucks and dumper shall not reverse on gradient.
vA berm at
least half the diameter of the wheel of the largest dumper plying or one meter
whichever is greater and of adequate width provided at the edge of the spoil or
coal dump.
Small vehicle shall not be
allowed on the haul roads.separate road shall be provided at
For the small vehicle.
Only authorized vehicle shall be allowed
With raised red flag
in the daytime and redlight in the night.
The flag or light shall be visible for the dumper
operator from a distance
Of at least 30m.
Stander of
illumination-Roadways and footpath from bench to bench – minimum standard of
illumination 3 Lux horizontal.
Factors responsible for slope failure
vSlope
angle
vGeo
mechanical properties of slope materials.
vPresence
and orientation of faults and other discontinues.
vPresence
of water.
vDepth of
the pit.
vEffect
of blasting.
vPresence
of u.g. working.
vPresence
of fire
vPresence
of week bed in the OB
vUndercutting
or toe cutting
v
PROBLEMS ACCOCIATED WITH
HIGHWALL
1.Because of
jointing , slabbing etc.
probability associated with
Slope failure increases.
2.It will require deep
hole blasting with heavy amount of explosives.
Which will produce
vibration, fly rocks, boulders air blast etc.
3.Because of slope
failure or boulder falling from the top ,severe damages of machineries
And serious accident to
persons.
4.Supervision is
difficult.
5.Water pressure in the
joint responsibility for more frequent slope failure.
6. Problem of floor
sliding due to presence of aquifers.
Precaution-
1.Angle of
slope of the bench should be equal or less than angle of repose of the bench
rock. For dragline bench angle of slope of the high wall benches varies from
70-80 deg.
2.Face
should form an angle with the main cleats, fractures etc.
3.Bench dose
remain for long time, quick rate of advance.
4.Controlled
blasting should be practiced..
5.Highly
charged water bearing strata should be dewatered by putting boreholes with
pumps.
6.Weak plane
in the strata should be cement groued.
7.Bench ht.
should not be more than required.
8.Design and
review shall be done by experts from
CMRI,CMPDIL etc.
9.Undercutting
and toe cutting should be avoided.
EFFECTIVE DRAINAGE
1.The quarry should
provided with effective garland drains.
2. The benches should have effective toe drains.
3.Stablity may be improved
by effective drainage of the slope . Horizontal holes are drilled in to the
slope face for effective drainage &
to reduce water pressure. Holes are drilled at angle of 5 degree will facilitate
free flow of water. Holes may be 10-15 deep at intervals of 5m or less. A pipe
inserted in to the hole to prevent caving. The pipe should be perforated.
SPOIL BANK
1.Slope of spoil bank face shall be determined by the natural angle of
repose of the material, but shall not in no case exceed 37.5 degree from the
horizontal.
2.The
spoil bank face shall not be retained by artificial means at an angle in excess
of natural angle of repose. Any spoil bank exceeding 30m in ht. , should be
benched so that no bench exceed 30m ht. and general slope does not exceed I1 vertiacal to
1.5 horizontal.
3.Incase of working by dragline ,where the inclination of the bed rock does not exceed 5 deg. From the
horizontal, the ht of
overburden dump shall not exceed 60m.A bench of 10- 15m wide in overburden
overburden shall be maintained between these dumps and final dump created by
the dragline. If the inclination of the bed rock exceeds 5 deg., the ht. of the
forebank
shall be suitably planned.
3.The toe of the spoil bank
shall not allowed to reach a railway or other public works or other public
roads or building or other permanent structure not belonging to the owner of
the mine closer than a distance equal to the vertical ht. of the
face.
4. A suitable fence
shall be erected between any roadway or public works or road or building or
structures and toe of the active spoil bank at a distance of not less than ht of the
spoil bank.
5.No persons shall
be permitted to approach near the toe of
an active spoil bank.
6. The manager shall
appoint the sufficient no. of competent persons to supervise dumping operation.
7. The manager shall
formulate Dumping rules which shall specf
y
a.The
provision of system of drainage
b.System of inspection
c.Maximum
ht. of the bench. The ht of the shall not exceed 60m .
8.
Comments
Post a Comment